Instruction
For Erection And Use To Be Followed Carefully
Step1
Fit a horizontal (
short ) brace
Onto the vertical
member of
One frame, resting
directly onto the
Alloy casting at the
first horizontal rung
Tigger face to outside of the tower.
Step2
Join second base frame
to first
ensuring brace hook again rests
directly onto alloy
casting.
Fit second horizontal
brace in
corresponding position.
Level around base of
tower by
Moving a spirit level,
in sequence,
Around the 3 starred
positions making adjustments as necessary.
Step3
Fit first diagonal
brace pair from
First to third rung as
close to the
Vertical member upright
tube as possible.
Fit second diagonal
brace
pair on the other side
of the
Tower in the opposite
direction.
Step4
Locate temporary
platform on second rung
Of the tower and
install second lift of
Frames ensuring ladder
line up.
The wind lock device
will
Automatically engage.
Step5
Continue with step 3
& 4
Until height required.
Attach one stabilizer
to each corner of tower
And each brace and
assemble guardrails and platform